The last phase of construction for the Southport Levee Improvement Project started at the end of May. This final phase brings material from Elk Grove to restore the parcels where material was sourced to construct the Southport setback levee.
WSAFCA completed the hauling portion for the Borrow Restore Project in the first week of August. To mitigate for the haul trucks using Gregory Avenue, WSAFCA included a line item to slurry seal the roadway after the haul. Before the contractor applied the slurry seal, WSAFCA worked with Public Works to repair damaged pavement, fill potholes, and seal some cracks. The repairs by Public Works prior to the slurry seal made for a better finished product. Now that the repairs and slurry seal are complete, new striping will be applied to the roadway next week.
Video: 2018 Southport Levee
Phase 2 - Southport Levee Improvement Project
Lead Agency: WSAFCA
Project Stage: Construction completed.
Project Details: WSAFCA has completed construction of the Southport Levee Improvement Project which involves the construction of flood risk-reduction measures along the Sacramento River South Levee in the city of West Sacramento. Levee improvements included a combination of fix in place and a new setback levee embankment construction with cutoff walls, seepage berms, utility relocation, demolition, rock slope protection, and the use of borrow sites. Project transportation improvements included realigned roadways, new access ramps and roads, turnouts, cul-de-sacs, and maintenance corridors. Constructed flood risk-reduction measures addressed deficiencies of through-seepage, under-seepage, slope stability and geometry, erosion, encroachments, and noncompliant vegetation. WSAFCA's goal is to achieve a 200-year level minimum of levee performance for the City of West Sacramento. The project would bring the levee up to standard with Federal and State levee design criteria, as well as provide opportunities for ecosystem restoration and public recreation.
Levee Length: 5.6 miles, extending from river mile 57.2 to river mile 51.6 within the Sacramento River South Levee
Construction Cost: $80,000,000 estimated
Phase 1 - Village Parkway Improvements (South)
Lead Agency: WSAFCA
Project Stage: Construction completed
Project Details: As the first phase of the Southport Sacramento River Early Implementation Project, WSAFCA has completed construction of the Village Parkway South project. Village Parkway South is a three-mile stretch of roadway that will replace segments of South River Road and provide property access to residents before levee construction begins. The Village Parkway South improvements included a 36 foot wide paved roadway with 2 lanes with bicycle lanes along with associated residential access roads, drainage improvements, signing and striping, and water pollution controls. The City of West Sacramento’s General Plan already identifies the construction of Village Parkway but due to the levee improvements, construction is starting 10 years earlier than previously anticipated.
Roadway Length: 3 miles and associated access roads
Construction Cost: $5,000,000 estimated